Pla 80 HOV Phase 2

Description: Near Sacramento, west of Sacramento/Placer County line to just west of Miner's Ravine. Add eastbound and westbound HOV lanes and auxiliary lanes with bridge widening and ramp modifications.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Citrus Heights, Roseville
Zip Code 95621, 95661, 95678
 
Senate District
01, 06
Assembly District 04, 05
Congressional District 03, 04
 
Caltrans District
03
 
 
County/State Route Placer 80
Postmile Begin/End 0 2.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2243    2,243  
Peak Period Time Savings (minutes)  151850    151,850  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Design (PS&E) Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Right of Way Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
Construction Phase
Caltrans Jonathan Pray (530) 740-4920   jonathan.pray@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$17,700 $-9,507 $8,193
Non-bond Funding
State/Federal*
$4,000 $0 $4,000
Local**
$58,532 $-23,439 $35,093
 
Total**** $80,232 $-32,946 $47,286

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,900 $236 $2,136 $2,067
Design(PS&E)
$5,000 $1,498 $6,498 $6,937
Right of Way
$1,050 $-450 $600 $558
Construction
$72,282 $-34,230 $38,052 $35,567
 
Total* $80,232 $-32,946 $47,286 $45,129

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2001 

06/01/2004 
 

 
04/01/2001 

06/01/2004 
100  04/01/2001 

06/16/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2005 

12/01/2007 
 

 
12/01/2005 

12/01/2007 
100  12/01/2005 

11/30/2007 


Begin Right of Way Phase

End Right of Way Phase
11/01/2006 

09/01/2008 
 

 
11/01/2006 

09/01/2008 
100  09/15/2006 

11/27/2007 


Begin Construction Phase

End Construction Phase
05/01/2008 

10/01/2010 
 

 
05/01/2008 

10/01/2010 
100  05/01/2008 

10/18/2012 


-25 
Begin Closeout Phase

End Closeout Phase
10/01/2011 

10/01/2012 
 

 
10/01/2011 

10/01/2012 
50  10/18/2012 

09/30/2017 
-13 

-61 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009   
Implementation Date 07/01/2010    07/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2243 2,243
Peak Period Time Savings (minutes) 151850 151,850

Bond Funding Cost
Adopted:
$17,700,000
Current Approved:
$8,484,000
Actual Expenditures:
$8,268,000

 

Status as of December 31, 2023.